Pivotal Tracker for Project Management

We are using Pivotal Tracker to manage our Agile Development process.  This tool continues to support our use of User Stories and Point Estimation and provides a more convienent environment for Planners and Developers to collaborate in.

For an overview and training on Pivotal Tracker there are a number of helpful video tutorials linked below.

Iteration Report 13 Feb - 24 Feb 2012

Story Points Completed: 61.0 sp

Average Velocity: 65 sp/itr

Planning Meeting for Iteration 27 Feb - 9 Mar 2012

These are some rough planning notes for the coming Iteration.   

Notes on Current Development

GaLyn

We're adding details about search and advanced search of data in a richer way.  Ben helped shape the advanced search feature list.  There may be some graduate student work to help integrate Gephi at this point in time.  

Next Iteration:  Development

Open Emory

Iteration Report 30 Jan - 10 Feb 2012

Story Points Completed: 74.5 sp

Average Velocity: 65 sp/itr

Planning Meeting for Iteration 6 Feb - 17 Feb 2012

These are some rough notes related to planning for the upcomming Iteration.

Projects Current In Development

GaLyn

Iteration Report 16 Jan - 27 Jan 2012

Story Points Completed: 59.5 sp

Average Velocity: 56.3 sp/itr

Planning Meeting for Iteration 30 Jan - 10 Feb 2012

These are some rough notes related to planning for the upcomming Iteration

Projects In Development

Global Health Chronicles

IT Briefing 2012-01-19

UTS Briefing Notes -Thursday, Jan 19, 2012

[LearnLink Client upgrade]
There is a critical security bug in the Learnlink Client.
All users will be required to upgrade by 3/12/2012
If you are on version 10, you need to go to 10.014+
If you are on version 11, you need to go to 11.006+

Iteration Report 2 Jan - 13 Jan 2012

Story Points Completed:   61 sp

Average Velocity:  52 sp/itr

Planning Meeting for Iteration 16 Jan - 27 Jan 2011

These are some rough Notes and project updates created to plan for development needs in the upcomming iteration.

Projects In Development

Voyages

All known work is completing on Voyages in the current iteration and we expect the project to be in testing next iteration.

Next Iteration:  Testing

African Origins